SAN DIEGO— The Port of San Diego soon will begin improvements on the parking lot at Chula Vista Bayfront Park. Construction, set to start in July, is expected to be completed by Oct. 17. The project will be carried out in phases to ensure pedestrian and vehicle access in both directions, with traffic control measures in place to minimize disruptions.
What to Expect During the 90-Day Project:
- Park and boat launch access: Both will remain open throughout the project.
- Marina Way impact: A section of Marina Way will be affected.
- Traffic control: No detours are required, but measures will be implemented.
- Parking limitations: Parking will be limited, but an adjacent dirt lot will be available for use.
Project Phases:
- Phase 1: Late July to mid-August
- Phase 2: Mid-August to early September
- Phase 3: Early September to mid-September
- Phase 4: Mid-September to early October
These phases are subject to change based on construction conditions.
This project is part of the Port’s annual Major Maintenance Program. In April, the Board of Port Commissioners awarded a $1.45 million construction contract to Griffith Company.
Chula Vista Bayfront Park is located at 980 Marina Way. For more information about this project and the Chula Vista Bayfront redevelopment effort, visit portofsandiego.org/chulavistabayfront.