Coastal Commission Approves Seawall and Sand Replenishment Plan to Protect San Clemente Rail Line

SAN CLEMENTE — The California Coastal Commission approved a controversial shoreline protection plan Nov. 5 that will allow the Orange County Transportation Authority (OCTA) to construct a 1,223-foot seawall, install additional rock barriers, and replenish beaches along San Clemente’s vulnerable coastal rail corridor.

The project is intended to protect railroad tracks threatened by coastal erosion, rising tides and storm-driven waves, which have contributed to more than 12 months of emergency rail closures since 2021.

Under the approved plan, OCTA will place approximately 450,000 cubic yards of sand along southern San Clemente beaches and another 250,000 cubic yards between the San Clemente Pier and North Beach. The project also includes approximately 2,100 tons of additional rock reinforcement, which is expected to occupy about 3.5 acres of beach.

The approval follows years of debate over shoreline armoring, with environmental advocates and residents arguing that seawalls and rock barriers can accelerate beach erosion and reduce public access. Supporters maintain that protecting the rail corridor is essential to regional transportation and economic activity.

As part of the 10-year permit, commissioners required a five-year review to evaluate whether the sand replenishment adequately offsets the impacts of shoreline armoring. Additional conditions include public access improvements and a long-term railroad adaptation study.

The sand replenishment portion is estimated to cost approximately $94 million, with $305 million in state and federal funding already secured for coastal rail protection efforts.

For Southern California coastal communities, the decision highlights the ongoing challenge of protecting transportation infrastructure while preserving beaches, recreational access, and shoreline resources. The project could also influence future approaches to erosion management along the region’s coastline.

OCTA officials said they are reviewing the permit conditions and their implications for construction, long-term maintenance and funding.